Black start

City skyline at dusk with only a very few office building windows lit
Toronto during the Northeast blackout of 2003, which required black-starting of generating stations.

A black start is the process of restoring an electric power station, a part of an electric grid or an industrial plant, to operation without relying on the external electric power transmission network to recover from a total or partial shutdown.[1]

Power to restart a generating station or plant may come from an on-site black start standby generator. Alternatively, where a large amount of power is required, a tie-line to another generating plant or to an emergency generator may be used to start the facility. Once the main generating units are running, the electrical transmission network can be re-connected and electrical loads restored.

Black-start power may be ensured by an agreement where a particular energy supplier is paid to make black start power available when required. Not all generating plants are suitable for providing black-start power to a network.

Station service power

Electrical generating plants require electric power to operate systems required in the plant. For example, a coal-fuelled plant requires conveyors, crushers, air compressors, and combustion air fans to operate. Steam cycle plants require large pumps to circulate water for steam boilers and for cooling of condensate water. Hydroelectric plants require power to open intake gates, and to adjust the hydraulic turbines for speed regulation. Even a wind turbine plant may require a relatively small amount of electric power for such things as adjusting blade pitch and direction.

Normally, the electric power used within the plant is provided by the station's own generators. If all of the plant's main generators are shut down, station service power is provided by drawing power from the grid through the plant's transmission line. However, during a wide-area outage, off-site power from the grid is not available. In the absence of grid power, a so-called black start needs to be performed to bootstrap the power grid into operation.

Standby power sources

To provide a black start, some power stations or plant have small on-site diesel generators, normally called the black start diesel generator (BSDG), which can be used to start larger generators (of several megawatts capacity), which in turn can be used to start the main power station generators. Generating plants using steam turbines require station service power of up to 10% of their capacity for boiler feedwater pumps, boiler forced-draft combustion air blowers, and for fuel preparation. It is uneconomical to provide such a large standby capacity at each station, so black-start power must be provided over designated tie lines from another station.

Often hydroelectric power plants are designated as the black-start sources to restore network interconnections. A hydroelectric station needs very little initial power for starting purposes (just enough to open the intake gates and provide excitation current to the generator field coils) and can put a large block of power on line very quickly to allow start-up of fossil fuel or nuclear stations. Certain types of combustion turbine can be configured for a black start, providing another option in places without suitable hydroelectric plants.[2] In 2017, a utility in Southern California successfully demonstrated the use of an energy-storage system based on a lithium-ion battery to provide a black start, firing up a combined-cycle gas turbine from an idle state.[3]

Startup sequence

One method of black start (based on a real scenario) might be as follows:

  1. A battery starts a small diesel generator installed in a hydroelectric generating station.
  2. The power from the diesel generator is used to bring the generating station into operation.
  3. Key transmission lines between the station and other areas are energized.
  4. The power from the station is used to start one of the nuclear/fossil-fuel-fired base load plants.
  5. The power from the base load plant is used to restart all of the other power plants in the system.
  6. Power is finally re-applied to the general electricity distribution network and sent to the consumers.

Often this will happen gradually; starting the entire grid at once may be unfeasible. In particular, after a lengthy outage during summer, all buildings will be warm, and if the power were restored at once, the demand from air conditioning units alone would be more than the grid could supply. In colder climates, a similar issue can occur in winter with the use of heating devices.

In a larger grid, in addition to this "single island" ("bottom-up") approach, different strategies can be involved:[4][5]

  • multiple islands of generation (each with local power supplying local load areas) synchronizing and reconnecting to form a complete grid. The power stations involved have to be able to accept large step changes in load as the grid is reconnected;[6]
  • anchor ("core") island (also bottom-up);[7]
  • "backbone island" (bottom-up): backbone is restored first, thus allowing the outside assistance;[8]
  • top-down: backbone restored first with outside assistance;[9]
  • a combination of top-down and bottom-up approaches.[10]

There are multiple methods of commencing a black start of an island: hydroelectric dams, diesel generators, open cycle gas turbines, grid scale battery stores, compressed air storage, and so on. Different generating networks take different approaches, dependent on factors such as cost, complexity, the availability of local resources (e.g. suitable valleys for dams), the interconnectivity with other generating networks, and the response time necessary for the black start process.

Procurement of black start services

An operator at ERCOT

In the United Kingdom, the grid operator has commercial agreements in place with some generators to provide black start capacity, recognizing that black start facilities are often not economical in normal grid operation.[11] It is typical of power stations from the era of the Central Electricity Generating Board to have a number of open-cycle gas turbines (i.e. no heat recovery modules attached) that can run the entirety of the plant necessary to operate a full generating unit; these would normally be started by diesel generators, fed in turn by battery backups. Once up to speed, these gas turbines are capable of running the entire plant associated with the rest of the power station, negating the need to bring power in from other sources.

In the North American independent system operators, the procurement of black starting varies somewhat. Traditionally, the black-start capability was provided by integrated utilities and the costs were rolled into a broad tariff for cost recovery from ratepayers. In those areas which are not part of organized electricity markets, this is still the usual procurement mechanism. In the deregulated environment, this legacy of cost-based provision has persisted, and even recent overhauls of black-start procurement practices, such as that by the ISO New England, have not necessarily shifted to a competitive procurement, even though deregulated jurisdictions have a bias for market solutions rather than cost-of-service (COS) solutions.

In the United States, there are currently three methods of procuring black start. The most common is cost-of-service, as it is the simplest and is the traditional method. It is currently used by the California Independent System Operator (CAISO), the PJM Interconnection[12] and the New York Independent System Operator[13] (NYISO). The exact mechanisms differ somewhat the same approach is used, namely that units are identified for black start and their documented costs are then funded and rolled into a tariff for cost recovery.

The second method is a new method used by the Independent System Operator of New England[14] (ISO-NE). The new methodology is a flat-rate payment which increases black-start remuneration to encourage provision. The monthly compensation paid to a generator is determined by multiplying a flat rate (in $/kWyr and referred to as the $Y value) by the unit's Monthly Claimed Capability for that month. The purpose of this change was to simplify procurement and encourage provision of the black start service.

The final method of procurement is competitive procurement as used by the Electric Reliability Council of Texas[15] (ERCOT). Under this approach, ERCOT runs a market for black-start services. Interested participants submit an hourly standby cost in $/hr (e.g. $70 per hour), often termed an availability bid, that is unrelated to the capacity of the unit. Using various criteria, ERCOT evaluates these bids and the selected units are paid as bid, presuming an 85% availability. Each black-start unit must be able to demonstrate that it can start another unit in close proximity, in order to begin the islanding and synchronization of the grid.

In other jurisdictions there are differing methods of procurement. The New Zealand System Operator[16] procures the blackstart capability via competitive tender. Other jurisdictions also appear to have some sort of competitive procurement, albeit perhaps not as structured as that of ERCOT. These include the Alberta Electric System Operator,[17] as well as Independent Electric System Operator of Ontario,[18] both of which use a long-term "request for proposals" approach similar to New Zealand and ERCOT.

The first black start on Germany's grid was tested in 2017 at WEMAG battery power station in Schwerin on a disconnected, isolated grid. The WEMAG battery plant proved that it can restore the power grid after major disruption or blackout.[19]

Limitations on black start sources

Not all generating plants are suitable for black-start capability. Wind turbines are not always suitable for black start because wind may not be available when needed.[20] Wind turbines, mini-hydro, or micro-hydro plants, are often connected to induction generators which are incapable of providing power to re-energize the network.[21] In 2020, the 69 MW Dersalloch wind farm black-started part of the Scotland grid, using virtual synchronous machines.[22][23] The black-start unit must also be stable when operated with the large reactive load of a long transmission line. Many high-voltage direct current (HVDC) converter stations cannot operate into a "dead" system, either, since they require commutation power[clarification needed] from the system at the load end. A pulse-width modulation (PWM)-based voltage-source converter HVDC scheme has no such restriction.[24]

See also

References

  1. ^ Knight, U.G. Power Systems in Emergencies - From Contingency Planning to Crisis Management John Wiley & Sons 2001 ISBN 978-0-471-49016-6 section 7.5 The 'Black Start' Situation
  2. ^ Philip P. Walsh, Paul Fletcher Gas turbine performance, John Wiley and Sons, 2004 ISBN 0-632-06434-X, page 486
  3. ^ "California battery's black start capability hailed as 'major accomplishment in the energy industry'". May 17, 2017.
  4. ^ Gevorgian et al. 2021, p. 3.
  5. ^ PJM 2018, pp. 102–118.
  6. ^ PJM 2018, pp. 103–106.
  7. ^ PJM 2018, pp. 107–109.
  8. ^ PJM 2018, pp. 110–112.
  9. ^ PJM 2018, pp. 113–115.
  10. ^ PJM 2018, pp. 116–118.
  11. ^ Introduction to Black Start Archived 2006-05-21 at the Wayback Machine (National Grid plc) Covers technical and commercial background.
  12. ^ See PJM Tariff: Schedule 6A of the PJM Tariff, available online at: http://www.pjm.com/documents/downloads/agreements/tariff.pdf Archived 2008-12-09 at the Wayback Machine and Blackstart Business Rules, available online at: http://www.ieso.ca/Documents/consult/se16/se16_DACP-SWG-20060216-pjm-blackstart.pdf Archived 2014-12-16 at the Wayback Machine
  13. ^ See the NYISO Accounting and Billing Manual, 2006, available online at: http://www.nyiso.com/public/webdocs/documents/manuals/administrative/acctbillmnl.pdf Archived 2012-02-17 at the Wayback Machine NYISO Ancillary Services Manual 2006, available at "NYISO (Documents - Manuals - Operations)". Archived from the original on 2008-09-12. Retrieved 2008-12-24. NYISO Tariff (2006) at Rate Schedule 5, starting page 91, Revised Sheet 311, and Rate Schedule 6, starting at Revised Sheet No. 269, available online at "Archived copy" (PDF). Archived from the original (PDF) on 2008-10-12. Retrieved 2008-12-24.{{cite web}}: CS1 maint: archived copy as title (link)
  14. ^ See ISO-NE "Order Accepting Application" Docket No. ER03-291, Federal Energy Regulatory Commission, Issued Feb. 14 2003, available online at http://www.iso-ne.com/committees/comm_wkgrps/trans_comm/tariff_comm/mtrls/2006/may162006/index.html ISO-NE Open Access Transmission Tariff 2006 at p. 311, available online at "ISO New England - Open Access Transmission Tariff (OATT)". Archived from the original on 2008-10-25. Retrieved 2008-12-24. ISO-NE A3 Black Start Working Group Memo to the NEPOOL Transmission Committee, May 9, 2006 available online at http://www.iso-ne.com/committees/comm_wkgrps/trans_comm/tariff_comm/mtrls/2006/may162006/index.html
  15. ^ See ERCOT Protocols Section 6, 2006 available online at: "ERCOT - Current Protocols". Archived from the original on 2008-11-22. Retrieved 2008-12-24. ERCOT's bidding form is available online at: http://www.ercot.com/mktrules/protocols/current/22-%28A%29BlackStart-050105.doc
  16. ^ Electricity Commission of New Zealand (2005-11-01). "Electricity Governance Rules, Schedule C5 - Procurement Plan" (PDF). pp. 180–182. Archived from the original (PDF) on 2006-10-07. Retrieved 2008-12-24.
  17. ^ See http://www.aeso.ca/files/Nov05_BlackstartPP_v1.pdf Archived 2009-03-18 at the Wayback Machine
  18. ^ See "Ancillary Services". Archived from the original on 2008-12-28. Retrieved 2008-12-24.
  19. ^ Hales, Roy L. (August 15, 2017). "First Black Start On Germany's Grid". CleanTechnica.
  20. ^ Fox, Brendan et al; Wind Power Integration - Connection and System Operational Aspects, Institution of Engineering and Technology, 2007 ISBN 978-0-86341-449-7 page 245
  21. ^ George G. Karady, Keith E. Holbert, Electrical Energy Conversion and Transport: An Interactive Computer-Based Approach, John Wiley & Sons, 2013, ISBN 1118498038 page 9-57
  22. ^ Reid, Scott (3 November 2020). "ScottishPower in 'pioneering world first' after wind farm black-out boost". www.scotsman.com. The Scotsman. Archived from the original on 5 November 2020.
  23. ^ "Innovation". Scottish Power Renewables. 3 November 2020. Archived from the original on 3 November 2020.
  24. ^ Beaty, H. Wayne; Fink, Donald G. (ed) Standard Handbook for Electrical Engineers (15th Edition), McGraw-Hill 2007 ISBN 978-0-07-144146-9 page 15-22

Sources

Further reading

Read other articles:

Russian Long Range Aviation formation 326th Night Bomber Aviation Division (1943–1944) 326th Bomber Aviation Division (1944–1951) 326th Heavy Bomber Aviation Division (1951–present)Active1943–presentCountry Soviet Union (1943–1991)  Russia (1992–present)BranchSoviet Air Force (1943–1991) Russian Air Force (1992–2015)Russian Aerospace Forces (2015-present)TypeBomber Aviation divisionRoleStrategic bombingGarrison/HQUkrainkaEngagementsWorld War II Battle of the Korsun-Cher…

مجموعة إثنيةمعلومات عامةصنف فرعي من مجموعة سكانيةهوية ممثلة بـ إثنيةثقافةلغة أم تعديل - تعديل مصدري - تعديل ويكي بيانات  ميّز عن مجموعة عرقية.جزء من سلسلة مقالات حولعلم الإنسان المجالات الأثار علم الإنسان الحيوي علم الإنسان الثقافي اللغويات الاجتماعيات مواضيع علم الأ…

Town in Mississippi, United StatesAlligator, MississippiTownLocation of Alligator, MississippiAlligator, MississippiLocation in the United StatesCoordinates: 34°5′19″N 90°43′14″W / 34.08861°N 90.72056°W / 34.08861; -90.72056[1]CountryUnited StatesStateMississippiCountyBolivarArea[2] • Total1.04 sq mi (2.70 km2) • Land0.98 sq mi (2.55 km2) • Water0.06 sq mi (0.15 km…

ParadiseSingel oleh Coldplaydari album Mylo XylotoDirilis12 September 2011FormatUnduhan musikGenrePop rock, R&B[1]Durasi4:38LabelParlophonePenciptaGuy Berryman, Jonny Buckland, Will Champion, Chris MartinProduserMarkus Dravs, Dan Green, Rik SimpsonVideo musikParadise di YouTube Paradise adalah sebuah lagu oleh band rock alternatif Britania Raya Coldplay. Lagu ini dirilis pada 12 September 2011 sebagai singel kedua dari album ke-5 mereka, Mylo Xyloto.[2] Lagu ini melakukan deb…

Мост Мольткенем. Moltkebrücke 52°31′19″ с. ш. 13°22′08″ в. д.HGЯO По мосту проходит путь сообщения[d] Пересекает Шпре Место расположения Митте Конструкция Материал old red sandstone[d] Число пролётов 3 Общая длина 77,6 м Ширина моста 26,7 м Эксплуатация Открытие 1891 …

島嶼地區(英語:Insular area)特指那些不屬于美國五十州以及聯邦特區的美國属地[1]。 定義 在美國國務院使用的術語“島嶼地區”不僅指這些在美國主權之下的領土,還可以指代某些與美國已經簽署一項自由聯合協約獨立的國家。這些國家參加許多其他國內的程序,他們在法律上有別於美國和其居民。因而這些國家的居民不是美國公民或國民。 法定權利與義務 這些有…

「アプリケーション」はこの項目へ転送されています。英語の意味については「wikt:応用」、「wikt:application」をご覧ください。 この記事には複数の問題があります。改善やノートページでの議論にご協力ください。 出典がまったく示されていないか不十分です。内容に関する文献や情報源が必要です。(2018年4月) 古い情報を更新する必要があります。(2021年3月)出典…

Chronologies Données clés 1911 1912 1913  1914  1915 1916 1917Décennies :1880 1890 1900  1910  1920 1930 1940Siècles :XVIIIe XIXe  XXe  XXIe XXIIeMillénaires :-Ier Ier  IIe  IIIe Chronologies géographiques Afrique Afrique du Sud, Algérie, Angola, Bénin, Botswana, Burkina Faso, Burundi, Cameroun, Cap-Vert, République centrafricaine, Comores, République du Congo, République démocratique du Congo, Côte d'Ivoire, Djibouti, Égypte, …

Literary honour in Gujarat, India Kavi Kag AwardAward for contributions to LiteratureAwarded forPresented for the contribution to Gujarati-folk and Charan literatureSponsored byKavi Kag TrustReward(s)₹51,000 (US$640) eachFirst awarded2002Last awarded2023Total103Total awarded posthumously28Websitekavikag.comKavi Kag Award (Gujarati: કવિ કાગ ઍવોર્ડ) is an annual award named after the Gujarati poet Dula Bhaya Kag, given to folk artists, writers, scholars and institutions f…

2007 video game This article is about the cross-platform videogame. For the Game Boy Advance version of the game, see TMNT (Game Boy Advance video game). For other uses, see Teenage Mutant Ninja Turtles (disambiguation). This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: TMNT video game – news · newspapers · books …

United States historic placeBerkeley Women's City ClubU.S. National Register of Historic PlacesCalifornia Historical Landmark No. 908[1]Berkeley Landmark No. 2 The Berkeley City ClubShow map of Oakland, CaliforniaShow map of CaliforniaShow map of the United StatesLocation2315 Durant AveBerkeley, CaliforniaCoordinates37°52′03″N 122°15′46″W / 37.8676°N 122.2628°W / 37.8676; -122.2628Built1929ArchitectJulia MorganNRHP reference…

Disbanded British cavalry unit For the drum corps, see 27th Lancers Drum and Bugle Corps. 27th LancersCap Badge of the 27th Lancers ca 1941[1]Active1941–1945Country United KingdomBranch British ArmyTypeCavalry RegimentRoleReconnaissanceSize1 RegimentMilitary unit The 27th Lancers was a British Army cavalry regiment from 1941 to 1945. History The regiment was raised in June 1941 from a cadre of personnel taken from the 12th Royal Lancers. It was assigned to the 11th Armoured Divisi…

يوغوسلافالتعداد الكليالتعداد حوالي 444,000مناطق الوجود المميزةالبلد  القائمة ... يوغوسلافياصربياكرواتياسلوفينياالبوسنة والهرسكمقدونيا الشماليةالجبل الأسودألمانياالولايات المتحدة  الولايات المتحدة 327,131 (2010) كندا 65,305 (2006) أستراليا 26,883 (2011) صربيا 23,303 (2011) الجبل …

Volkswagen ID.7Descrizione generaleCostruttore Volkswagen Tipo principaleberlina Produzionedal 2023 Sostituisce laVolkswagen Passat Altre caratteristicheDimensioni e massaLunghezza4961 mm Larghezza1862 mm Altezza1538 mm Passo2966 mm AltroAssemblaggioZwickau, GermaniaFoshan (FAW-VW), Cina Stessa famigliaVolkswagen ID.5, Cupra Tavascan, Ford Explorer EV Auto similiTesla Model S, Xiaomi SU7 La Volkswagen ID.7 è un'autovettura elettrica prodotta dalla casa automobilistica t…

Method of evaluating certain integrals along paths in the complex plane This article is about the line integral in the complex plane. For the general line integral, see Line integral. Part of a series of articles aboutCalculus ∫ a b f ′ ( t ) d t = f ( b ) − f ( a ) {\displaystyle \int _{a}^{b}f'(t)\,dt=f(b)-f(a)} Fundamental theorem Limits Continuity Rolle's theorem Mean value theorem Inverse function theorem Differential Definitions Derivative (generalizations) Differ…

Species of bird Pheasant-tailed jacana The breeding plumage is marked by the elongated central tail feathers, white front and wing, and the silky golden nape feathers Conservation status Least Concern  (IUCN 3.1)[1] Scientific classification Domain: Eukaryota Kingdom: Animalia Phylum: Chordata Class: Aves Order: Charadriiformes Family: Jacanidae Genus: HydrophasianusWagler, 1832 Species: H. chirurgus Binomial name Hydrophasianus chirurgus(Scopoli, 1786) Synonyms Parra chinensis…

Daigunder爆闘宣言ダイガンダー(Bakutō Sengen Daigandā)GenreMecha, Aksi, Komedi Seri animeSutradaraHiroyuki YanoStudioBrains BasePelisensi Animation International Ltd.SaluranasliAnimax (2002)TV Tokyo (2002)Saluran bahasa Inggris JetixTayang 5 April 2002 – 27 Desember 2002Episode39  Portal anime dan manga Daigunder (爆闘宣言ダイガンダーcode: ja is deprecated , Bakutō Sengen Daigandā) adalah serial anime tentang manusia yang menggunakan robot dalam turnamen. Dibuat…

Shopping mall in South Carolina, United StatesHaywood MallEntrance to Haywood Mall, October 2012LocationGreenville, South Carolina, United StatesCoordinates34°51′00″N 82°20′00″W / 34.85°N 82.333333°W / 34.85; -82.333333Opening dateJuly 30, 1980DeveloperHaywood Mall AssociatesManagementSimon Property GroupOwnerSimon Property GroupNo. of stores and services172No. of anchor tenants5 (4 open, 1 vacant)Total retail floor area1,237,411 sq ft (114,959.2…

هذه المقالة تحتاج للمزيد من الوصلات للمقالات الأخرى للمساعدة في ترابط مقالات الموسوعة. فضلًا ساعد في تحسين هذه المقالة بإضافة وصلات إلى المقالات المتعلقة بها الموجودة في النص الحالي. (مارس 2023) غيديس     الإحداثيات 43°03′29″N 76°13′08″W / 43.058055555556°N 76.218888888889°W / 43.05…

高速自動車国道(有料) E27 舞鶴若狭自動車道 地図 路線延長 161.8 km 制定年 1972年(昭和47年) 開通年 1987年(昭和62年) - 2014年(平成26年) 起点 吉川JCT(兵庫県三木市) 主な経由都市 三田市、丹波篠山市、福知山市、舞鶴市、小浜市、敦賀市 終点 敦賀JCT(福井県敦賀市) 接続する主な道路(記法) E2A 中国自動車道E72 北近畿豊岡自動車道E9 京都縦貫自動車道E8 北陸自動車…