The Beijing underground cross-city railway is a short railway connection in Beijing. This railway line includes the Qiansanmen Tunnel. The speed limit is 120 km/h.[1] It connects the important transportation hubs Beijing railway station and Beijing West railway station via a tunnel. It also connects lines from southern and western areas with lines from northeast China.[3] The railway has a length span of 9.156 km (5.689 mi), and has been officially operational since March 20, 2015.[4]
In the early 1980s a plan was proposed to connect Beijing railway station to Beijing West railway station via a conventional railway. This was an important part of the overall planning of Beijing West railway station's renovation, originally announced as part of the "Eighth Five-Year Plan". However, due to technical difficulties and other factors, this project did not begin.
December 24, 2005: A proposal was made with the aim of completing the construction within 2.5 years, in time for the 2008 Beijing Olympic Games.[3][7] However, in 2007, the project was delayed and couldn't be completed before the Beijing Olympics.
July 2013: The construction project was successfully completed[8]
December 19, 2014: The line passed static inspection.
December 30, 2014: Test trains tested on the tracks.[9]
March 20, 2015: Beijing underground cross-city railway officially opened with the first trains running from Shijiazhuang to Chengde (K7742/7743, K7744/7741) train.[10]
October 11, 2022: Trains G7812/7813, G7814/7811 (Chengde South - Handan East) and G7816/7817, G7818/7815 (Chengde South - Shijiazhuang) started to use the tunnel, linking Beijing-Harbin HSR and Beijing-Guangzhou HSR.
Construction
Construction Unit: Beijing Railway Bureau
Construction Unit: China Railway Liu Ju Group Limited, China Railway 16 Bureau Group Co., Ltd., China Railway Bureau Group, a company tunnel
Designer: Third Railway Survey and Design Institute
Supervisor: Academy of Railway Sciences Engineering Construction Supervision Department, China Railway Engineering Consulting Corporation, Beijing Railway Construction Engineering Co. Ltd.
Main technical standards
Railroad grade: I level
Number of main lines: Double
Minimum curve radius: General area 800 meters, 550 meters in difficult sections