Hungerford Bridge and Golden Jubilee Bridges

51°30′22″N 0°07′12″W / 51.50611°N 0.12000°W / 51.50611; -0.12000

Hungerford Bridge
Hungerford Bridge and Golden Jubilee Bridges, seen from the north
Coordinates51°30′22″N 0°07′12″W / 51.5061°N 0.12°W / 51.5061; -0.12
CarriesSouth Eastern Main Line (Hungerford Bridge)
Pedestrians (Golden Jubilee Bridges)
CrossesRiver Thames
LocaleLondon
Maintained byNetwork Rail
Preceded byWestminster Bridge
Followed byWaterloo Bridge
Characteristics
DesignSteel truss (Hungerford Bridge) Cable-stayed bridge (Golden Jubilee Bridges)
History
Opened1864 (Hungerford Bridge)
2002 (Golden Jubilee Bridges)
Location
Map
Audio description of the bridges by Sophie Thompson

The Hungerford Bridge crosses the River Thames in London, and lies between Waterloo Bridge and Westminster Bridge. Owned by Network Rail Infrastructure Ltd (who use its official name of Charing Cross Bridge) it is a steel truss railway bridge flanked by two more recent, cable-stayed, pedestrian bridges that share the railway bridge's foundation piers, and which are named the Golden Jubilee Bridges.[1][2][3]

The north end of the bridge is Charing Cross railway station, and is near Embankment Pier and the Victoria Embankment. The south end is near Waterloo station, County Hall, the Royal Festival Hall, and the London Eye. Each pedestrian bridge has steps and lift access.

History

c. 1845 photograph of the bridge by Fox Talbot

The first Hungerford Bridge, designed by Isambard Kingdom Brunel, opened in 1845 as a suspension footbridge. It was named after the then Hungerford Market, because it went from the South Bank, specifically a northern point of Lambeth, soon close to London Waterloo station to that place on the north side of the Thames, specifically to the market (later Charing Cross Station) about 200 yards or metres east of Trafalgar Square partly in the parish of Saint Martin in the Fields, Westminster, the spire of which can be seen from the bridge.[1][4][5][6]

In 1859 the original bridge was bought by the railway company extending the South Eastern Railway into the newly opened Charing Cross railway station. The railway company replaced the suspension bridge with a structure designed by Sir John Hawkshaw, comprising nine spans made of wrought iron lattice girders, which opened in 1864.[5][6][7] The chains from the old bridge were re-used in Bristol's Clifton Suspension Bridge. The original brick pile buttresses of Brunel's footbridge are still in use, though the one on the Charing Cross side is now much closer to the river bank than it was originally, due to the building of the Victoria Embankment, completed in 1870. The buttress on the South Bank side still has the entrances and steps from the original steamer pier Brunel built on to the footbridge.[5]

Claude Monet oil painting, 1899, one of 37 versions from his Charing Cross Bridge series

To compensate for the removal of the footbridge, walkways were added on each side, with the western one later being removed when the railway was widened. Another walkway was temporarily added in 1951 when an Army Bailey bridge was constructed for the Festival of Britain. In 1980 a temporary walkway was erected on the western side while the eastern railway bridge and walkway were refurbished. It is one of three bridges in London to carry pedestrians and rolling stock; the others being Fulham Railway Bridge and Barnes Bridge.[1][4][6]

The footbridge gained a reputation for being narrow, dilapidated and dangerous; it was the scene of a murder in 1999.[8] In the mid-1990s a decision was made to replace the footbridge with new structures on either side of the existing railway bridge, and a competition was held in 1996 for a new design.

Further justification for new footbridge structures on the west flank and east flank was that the brittle wrought iron support pillars of Sir John Hawkshaw's railway bridge were vulnerable to impact from riverboats.[9] It was felt, especially following the Marchioness disaster, that these should be clad in concrete at water level; but the bridge's owners, Railtrack, could not afford the work. The Golden Jubilee Bridges achieved this protection at no cost to Railtrack.

The new footbridges

The concept design for the new footbridges was won by architects Lifschutz Davidson Sandilands and engineers WSP Group.[6][9] Detailed design of the two bridges was carried out by consulting engineers Gifford, now Ramboll UK. The steelwork for the new footbridges was fabricated by Butterley Engineering Ltd. of Ripley, Derbyshire.[10]

Their construction was complicated by the need to keep the railway bridge operating without interruptions, the Bakerloo line tunnels passing only a few feet under the river bed, and the potential danger of unexploded World War II bombs in the Thames mud.[6][9] Despite extensive surveys of the riverbed, London Underground was unwilling to accept these risks and preliminary works were stopped in 2000.[6] The design was modified so that the support structure on the north side, which would have been within 15 m (49 ft) of the tube lines, was moved out of the river bed and onto Victoria Embankment. Excavation near the tube lines was carried out when the tube was closed, and foundations were hand-dug for additional security.

The two new 4-metre (13 ft) wide footbridges were completed in 2002. They were named the Golden Jubilee Bridges, in honour of the Golden Jubilee of Elizabeth II, although in practice they are often still referred to as the "Hungerford Footbridges".

The Hungerford and Golden Jubilee bridges as seen from the London Eye, with Waterloo Bridge in the background

The 300 m (980 ft) long decks were raised using an innovative method called incremental launching, in which each 50 m (160 ft) long section was pulled across the river using a 250 m (820 ft) long steel truss weighing 300 tonnes. This process was repeated five times until each deck spanned the river, supported by six temporary piers made of steel and concrete. The seven 25-tonne pylons were then raised over the subsequent two weeks. Once the pylons had been installed, the decks were jacked up to enable their connection with the cable stays suspended from the pylons. The concrete deck was then lowered into its final position and the temporary piers and supports were dismantled.[9]

The design of the bridges is complex. Each of the two decks is supported by inclined outward-leaning pylons. The decks are suspended from fans of slender steel rods called deck stays—there are 180 on each deck, made up of over 4 km (2.5 mi) of cable—and are held in position by other rods called backstays. Because the pylons lean the back stays are under tension. The deck is secured in place by steel collars fitted around (although not supported by) the pillars of the railway bridge; the collars are themselves attached to the bridge's foundations by tie-down rods. The entire structure is thus held in place by exploiting the tensions between the pylons and the various stay rods and struts.[9]

Class 375 EMU on Hungerford Bridge

The new bridges won the Specialist category in the Royal Fine Art Commission Building of the Year Award in 2003. It gained a Structural Achievement Award commendation in the 2004 Institution of Structural Engineers awards, and has won awards from the Civic Trust and for its lighting design.[11]

In 2014, the planning application for the now cancelled Garden Bridge, revealed in its assessment of pedestrian movement across the Thames that the footbridges are the busiest in London, with an estimated footfall of 8.5 million each year.[12]

In fiction

See also

References

  1. ^ a b c Sir Howard Roberts and Walter H. Godfrey (1951). "Hungerford or Charing Cross Bridge". University of London & History of Parliament Trust. British History Online. Retrieved 26 February 2013.
  2. ^ London SE1 Community website (2 July 2003). "Princess opens gleaming Golden Jubilee Bridge". Bankside Press. Retrieved 26 February 2013.{{cite web}}: CS1 maint: numeric names: authors list (link)
  3. ^ Waldman, Melanie (8 December 2010). "Golden Jubilee Bridges". BootsnAll Travel Network. Archived from the original on 12 June 2017. Retrieved 26 February 2013.
  4. ^ a b Bevan, Frances (7 June 2012). "Hungerford Bridge". Status, Scandal and Subterfuge. Swindon Heritage. Retrieved 26 February 2013.
  5. ^ a b c Keeling, Gary. "Hungerford Bridge (1845)". MyBrunel.co.uk. Retrieved 26 February 2013.
  6. ^ a b c d e f Gilbert, David (15 December 2010). "Banister Fletcher Lecture 2010: David Gilbert "A short history of London in wrought iron"". London Society Journal (461). Retrieved 26 February 2013.
  7. ^ Where Thames Smooth Waters Glide
  8. ^ "Bridge murder gang get life". BBC News. 19 May 2000. Retrieved 4 May 2010.
  9. ^ a b c d e WSP Cantor Seinuk Gifford (5 August 2003). "Golden Jubilee (Hungerford) footbridge". Engineering Timelines. Archived from the original on 11 January 2015. Retrieved 26 February 2013.
  10. ^ Hungerford Bridge, Grace's Guide to British Industrial History, https://www.gracesguide.co.uk/Golden_Jubilee_Bridges, retrieved 22/10/2022.
  11. ^ "Project information (text preceded by impressive photos) at Lifschutz Davidson Sandilands website". Archived from the original on 15 April 2017. Retrieved 6 February 2014.
  12. ^ Garden Bridge Planning Application: Transport Assessment (Report). Garden Bridge Trust. 23 May 2014. pp. 62, 63. High level annual pedestrian demand data was obtained for other local bridges across the River Thames. The data consisted of a mixture of existing TfL surveys and surveys commissioned specifically for the Garden Bridge.
  13. ^ "Hungerford Bridge". Lightspeed Magazine. 17 May 2016. Retrieved 31 December 2018.
  14. ^ "Ambit". Ambitmagazine.co.uk. Archived from the original on 14 December 2018. Retrieved 31 December 2018.