The DND/ Maharani Bagh interchange and Kalindi Kunj metro are the 2 entry points in the state of Delhi. In Haryana, it passes entirely through existing Faridabad bypass road. The HSVP has transferred the Faridabad bypass to NHAI for the construction of NH–148NA highway. The construction work was started in May 2021 and 20 km stretch from KMP interchange to NH-2 interchange at Kail Gaon (Ballabhgarh) has been opened on 12 February 2023.
The 26km part from Sector 65 to Sohna in Faridabad has been opened for traffic in 2023.[4]
The 24 km long stretch from Jaitpur/ Mithapur in Delhi to Sector-65 in Faridabad has been opened to public on 12 November 2024.[5] The remaining 9 km part from Mithapur to DND would be ready by May 2025.
7 km out of 9 km route of Package-1 in Delhi state will be elevated with two-level crossings at 4 locations of the Delhi Metro rail line (near Okhla Vihar and Kalindi Kunj metro station), making it the 1st expressway in India to cross above elevated metro rail line. NH-148NA exits Delhi at MCD Toll Plaza (near Mithapur) which is 12.5 km from the DND starting point.
Packages
The NHAI has divided the construction work of 59 km long DND–Faridabad–KMP section of Delhi–Mumbai Expressway project into three packages and awarded it to DRA Infracon. Its construction cost is around ₹5,332 crores (including land acquisition cost).[10][11]
The deadline of construction work of Package-2 and 3 (Haryana) is 24 months, while deadline of Package-1 (Delhi) is 30 months.
Jewar Airport link
The NHAI had announced in August 2021, that an additional 31 km long spur will also be constructed from Noida International Airport in Jewar to Faridabad bypass road on this expressway.[12] Tender for this Spur package has been awarded by the NHAI to Apco Infratech Pvt. Ltd. on 29 July 2022.
The construction work of Delhi–Mumbai Expressway is divided by NHAI into 4 sections with a total of 52 tenders/ construction packages as given below. The entire 1,350 km long expressway is expected to be completed by January 2025.
Feb 2021: Construction work is expected to start this year: NHAI.[16]
May 2021: Construction work started in Package-3 on 14 May 2021. Schedule completion is 24 months.
Aug 2021: Construction work started in Package-2 (Faridabad bypass) on 10 August. Schedule completion is 24 months.
Oct 2021:HSVP started demolishing illegal encroachments falling on the RoW in Faridabad.[17]
Jan 2022: Construction work started in Package-1 (Delhi) on 11 January. The deadline of Package-1 is June 2024 (30 months).
Mar 2022:Segment Launcher started erection of concrete structures in Maharani Bagh on 21 March. 7 km out of 9 km long (Package-1) is elevated.[18]
July 2022: Tender for Faridabad bypass to Jewar Airport (Spur package) has been awarded by the NHAI to Apco Infratech Pvt. Ltd. on 29 July.[19][20]
Feb 2023: The NHAI has opened 20 km stretch on Package-3, from Kail Gaon on NH-2 to KMP interchange at Khalilpur (Nuh district) on 12 February 2023.[21]
Aug 2023: The Package-2 (Jaitpur in Delhi to Sector-65, Faridabad bypass) has missed its 24 months deadline of 10 August 2023.
Feb 2024: Union Minister Nitin Gadkari inspected Package-1 & 2 followed by a press conference at DND on 14 February. He said project will be completed by 2024 end.[22]
Nov 2024: 24 km long Package-2 has been opened to public on 12 November 2024. It is from Jaitpur/ Mithapur in Delhi to Sector-65 in Faridabad.