Beleghata (also known as Metropolitan ), is a station of Line 6 of the Kolkata Metro located in Beleghata at Biswa Bangla Sarani , Dhapa of Kolkata , West Bengal , India , serving Beleghata and Metropolitan areas.[ 2] [ 3] [ 4] The station is elevated beside the Eastern Metropolitan Bypass .[ 5] [ 6] [ 7] [ 8]
Location
This station is located in Beleghata across the service road and footpath on the eastern side of Biswa Bangla Sarani .[ 9] [ 10] [ 11] The main elevated structure of the station is situated along the service road and footpath adjacent to the New Garia -bound lane of Biswa Bangla Sarani near the end of Maa Flyover .[ 12] [ 13] [ 14] It is geographically located at 22°33′03″N 88°24′15″E / 22.550703°N 88.404094°E / 22.550703; 88.404094 .[ 15] [ 16] [ 17] The previous station of the station is Barun Sengupta metro station at a distance of 0.9 km (0.56 mi) and the next station is Gour Kishore Ghosh metro station at a distance of 1.7 km (1.1 mi).[ 18] [ 19] [ 20]
History
Beleghata metro station
This project was sanctioned in the budget of 2010–11 by Mamata Banerjee with a project deadline of six years.[ 21] The execution of this project has been entrusted to RVNL at a cost of Rs 3951.98 crore.[ 22] It will help to reduce travel time between the southern fringes of Kolkata to Netaji Subhas Chandra Bose International Airport . In October 2011, RVNL awarded Gammon India Limited , the tender for the construction of the metro corridor from VIP Bazar Metro Station to Nikko Park (Nalban metro station ),[ 23] [ 24] including stations, as part of Package-II of Line 6.[ 25] Amongst those metro stations, one near Beleghata was also sanctioned.[ 26] [ 27] [ 21] In January 2012, the construction of the metro station along with the metro line started.[ 25] The construction of the station was stopped in 2015 due to land dispute at Tagore Park culvert and a pair of its own footover bridges .[ 28] The construction of the station started again in May 2017.[ 29] [ 30] [ 31] [ 32] [ 33] [ 34] But the metro couldn't be started due to a viaduct gap over Tagore Park culvert.[ 35] [ 36]
A week later after inauguration and a day after commercial run started on Kavi Subhash -Hemanta Mukhopadhyay section, in March 2024, RVNL announced the completion of that 76 m viaduct gap after construction of a single-span hanging steel bridge over the disputed Tagore Park culvert .[ 25] [ 37] This completed the viaduct upto Beleghata metro station, clearing the way for commercial operations at this station.[ 38] [ 39] [ 40] Trial runs have started in March 2024.[ 41] [ 10] [ 42]
As of November 2024, for the Beleghata station and the stretch from Hemanta Mukhopadhyay till IT Centre metro station to be inaugurated, construction of safety limit of 90 m (300 ft) metro viaduct beyond the station is completed but the footover bridge is yet to be connected from both side of road.[ 25] On the other hand, filling a 400 m (1,300 ft) gap over Chingrighata crossing has not started and construction of Gour Kishore Ghosh , Nalban and IT Centre metro station is yet to be completed.[ 17] The station is expected to be operational by mid-2025.[ 43] [ 44]
Station
Beleghata metro station
Structure
Beleghata Metro Station is an elevated metro station and has a total of 3 levels. Station entrances and exits begin or end at the first level or ground level . Second-level or L1 or intermediate level houses station fare control , station agents, metro vending machines , crossovers, etc.[ 45] The third level or L2 or the final level houses the platforms and rail tracks . The station is 200 meters long and 25 meters wide.[ 46] [ 47]
The station has four entrances and exits. The station is being built with state-of-the-art technology. In addition to staircases, it will be equipped with lifts and escalators . The station also has drinking water and toilet facilities.[ 46] [ 48]
Layout
Station with two tracks and two side platforms
Power and signal systems
Like other stations and lines of Kolkata Metro , this station has 750 volt DC powered third rail .[ 49] The electricity system will be used to operate the train.[ 50]
Train movement at this station will be managed by communication based train control signaling system. With this signal system, trains can be operated at intervals of 90 seconds.[ 51]
Services
Services have not started from this station. Currently the station is under construction and is set to be opened in 2024.[ 29] [ 9]
Connections
This section is empty. You can help by
adding to it .
(December 2024 )
See also
References
^ Chakraborty, Ajanta (20 February 2023). "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja" . The Times of India . Archived from the original on 22 February 2023. Retrieved 11 March 2023 .
^ Abbas, Ajmal (30 January 2023). "First phase of Kolkata Metro's Orange Line all set for launch; covers Kavi Subash to Hemanta Mukherjee in 7 minutes" . TimesNow . Archived from the original on 30 January 2023. Retrieved 11 March 2023 .
^ Staff Reporter (30 March 2024). "Kolkata Metro: CCRS Inspects Beleghata-Hemanta Muk. Stretch - Metro Rail News" . Retrieved 8 May 2024 .
^ Basu, Kinsuk. "Metro Railway accuses state government of non-cooperation; government refutes claim" . Telegraph India .
^ "TRIAL RUN FOR TRAFFIC DIVERSION NEAR BELEGHATA METRO STATION STARTED" .
^ "Trial run for traffic diversion near Beleghata Metro started" .
^ "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja" . The Times of India . 20 February 2023. ISSN 0971-8257 . Retrieved 23 August 2023 .
^ Staff Reporter (23 August 2023). "Kolkata Metro: GM Reviews Orange Line's Kavi Subhas to Airport Stretch" . Metro Rail News . Retrieved 23 August 2023 .
^ a b "Beleghata-Ruby Section of Kolkata Metro Undergoes Inspection, Here's Why" . News18 . 30 March 2024. Retrieved 8 May 2024 .
^ a b "Metro Railway Kolkata / Indian Railways Portal" . mtp.indianrailways.gov.in . Retrieved 8 May 2024 .
^ Ghosh, Shreya (26 April 2024). "Kolkata Metro: From Stations To Trial Runs, Here's All About The Ruby-Beleghata Stretch" . Curly Tales . Retrieved 8 May 2024 .
^ "Kolkata Metro: বাইপাসের উপর 'প্রায় তৈরি' নয়া মেট্রো স্টেশন, কবে জুড়বে গড়িয়া-এয়ারপোর্ট রুট?" . Aaj Tak বাংলা (in Bengali). Retrieved 8 May 2024 .
^ "Kolkata Metro conducts trial runs on Orange Line from Ruby Crossing to Beleghata | Metro Rail Today" . Metro Rail Today: Gateway to Rail & Metro Industry . Retrieved 8 May 2024 .
^ "Metro block after Bypass trial chaos" . The Times of India . 9 February 2024. ISSN 0971-8257 . Retrieved 8 May 2024 .
^ "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja" . The Times of India . 20 February 2023. ISSN 0971-8257 . Retrieved 8 May 2024 .
^ "Metro Railway Kolkata / Indian Railways Portal" . mtp.indianrailways.gov.in . Retrieved 8 May 2024 .
^ a b "Metro Railway Kolkata / Indian Railways Portal" . mtp.indianrailways.gov.in . Retrieved 8 May 2024 .
^ Staff Reporter (30 April 2024). "Kolkata Metro Conducts Trial Runs On New Orange Line Stretch - Metro Rail News" . Retrieved 8 May 2024 .
^ "Kolkata Metro Update: Trial runs to commence on extended Orange line from Ruby Crossing to Beleghata" . Financialexpress . 25 April 2024. Retrieved 8 May 2024 .
^ MPost (30 March 2024). "Min & Kolkata Police refute Metro's claim of non-cooperation from state" . www.millenniumpost.in . Retrieved 8 May 2024 .
^ a b "Rail set to take over East-West" . The Telegraph . Calcutta, India. 8 February 2011. Archived from the original on 13 February 2011.
^ " "Seven projects meant to change the face of Calcutta are entangled in a web of land politics and pandering. Metro explores the tunnel vision" " . Telegraph india .
^ "বরুণ সেনগুপ্ত মেট্রো স্টেশনের নির্মাণ কাজ তুঙ্গে, অন্দরমহলটা দেখে নিন" . Eisamay (in Bengali). Retrieved 8 May 2024 .
^ "Kolkata Metro Update: Chief Commissioner of Railway Safety inspects Beleghata-Ruby section" . Financialexpress . 30 March 2024. Retrieved 8 May 2024 .
^ a b c d MP, Team (29 March 2024). "Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay (Ruby) stretch" . www.millenniumpost.in . Retrieved 8 May 2024 .
^ "Details of tenders/contracts" (PDF) . Archived from the original (PDF) on 19 March 2020. Retrieved 30 March 2024 .
^ " "Road Ahead….. Projects sanctioned" " . mtp.indianrailways.gov.in . Retrieved 28 March 2024 .
^ " "Construction of VIP Bazar station begins after two years" " .
^ a b "Airport-New Garia Metro: Site visit next week to bridge VIP Bazar gap" . The Times of India . 12 March 2023. ISSN 0971-8257 . Retrieved 28 March 2024 .
^ "Man electrocuted at construction site" . The Times of India . 19 February 2024. ISSN 0971-8257 . Retrieved 28 March 2024 .
^ "শেষের মুখে কলকাতা মেট্রোর আরও ১ স্টেশনের কাজ! ভিতরটা কেমন হল? রইল 'ফার্স্ট লুক' " . Hindustantimes Bangla (in Bengali). 28 September 2023. Retrieved 29 March 2023 .
^ "মেট্রোর পথ করতে নোনাডাঙায় সরছে পুরোনো ভিআইপি বাজার" . Eisamay (in Bengali). Retrieved 28 March 2024 .
^ "CRS check till Metropolitan: No Ruby ops on Thurs, Fri" . The Times of India . 27 March 2024. ISSN 0971-8257 . Retrieved 29 March 2024 .
^ "Kolkata: Pipe bridge lifted out of Metro alignment" . The Times of India . 15 July 2020. ISSN 0971-8257 . Retrieved 29 March 2024 .
^ "Ritwik Ghatak Metro Station: ঋত্বিক ঘটক মেট্রো স্টেশনের কাজ শেষ পর্যায়ে, ফাস্ট লুকেই হাঁকাল ছক্কা! » Najarbandi 24X7" . najarbandi.in (in Bengali). 29 September 2023. Retrieved 29 March 2024 .
^ "Hanging bridge on Bypass solves Metro problem at Tagore Park" . The Times of India . 3 November 2023. ISSN 0971-8257 . Retrieved 29 March 2024 .
^ PTI (25 April 2024). "Kolkata Metro to start trial runs along Ruby-Beleghata stretch" . ThePrint . Retrieved 8 May 2024 .
^ "Traffic starts moving along Tagore Park western flank" . The Times of India . ISSN 0971-8257 . Retrieved 16 March 2024 .
^ "Kolkata Metro Orange Line Expands for Beleghata: Trials Start - TimesProperty" . timesproperty.com . Retrieved 8 May 2024 .
^ SNS (1 April 2024). "Blame game between Kolkata Metro, city police over Orange Line delays" . The Statesman . Retrieved 8 May 2024 .
^ "Kolkata Metro: Trial Runs Begin For Seamless Commutes From Ruby Crossing To Beleghata" . News18 . 26 April 2024. Retrieved 8 May 2024 .
^ "Metro Railway Kolkata / Indian Railways Portal" . mtp.indianrailways.gov.in . Retrieved 8 May 2024 .
^ "Metro Railway rues delay in getting NOC from police for construction work near Beleghata station" . The Telegraph Online .
^ "Metro Railway Kolkata / Indian Railways Portal" . mtp.indianrailways.gov.in . Retrieved 8 May 2024 .
^ "Metro Railway Kolkata / Indian Railways Portal" . mtp.indianrailways.gov.in . Retrieved 8 May 2024 .
^ a b "Ritwik Ghatak Metro Station: ঋত্বিক ঘটক মেট্রো স্টেশন চোখ ধাঁধানো, কাজ প্রায় শেষ, কেমন হল? দেখুন" . Aaj Tak বাংলা (in Bengali). Retrieved 29 March 2024 .
^ "Metro Railway Kolkata / Indian Railways Portal" . mtp.indianrailways.gov.in . Retrieved 8 May 2024 .
^ "নিউ গড়িয়া-বিমানবন্দর মেট্রো করিডোরে বড় খবর, নতুন স্টেশনের ছবি দেখুন" . Eisamay (in Bengali). Retrieved 29 March 2024 .
^ "Kolkata Metro update: Authorities conduct trial runs on extended Orange line from Ruby Crossing to Beleghata – Details inside" . Financialexpress . 28 April 2024. Retrieved 8 May 2024 .
^ MP, Team (29 April 2024). "Trial run by Metro from Hemanta Mukhopadhyay (Ruby) to Beleghata" . www.millenniumpost.in . Retrieved 8 May 2024 .
^ PTI (29 March 2024). "Beleghata-Ruby section of Kolkata Metro undergoes inspection" . ThePrint . Retrieved 8 May 2024 .